Article: “Oval Beach lot rebuild comes in under budget” (Commercial Record)

The City of Saugatuck has reason to celebrate – F&V recently completed their parking lot rebuild project for Oval Beach and it came in under budget.

The project included repaving and expanding the park entrance turnaround to accommodate recreational vehicles, removing five trees west of the entry booth. Seven parking spaces were added to the 500 already on site. The project came in about $6,000 less than the $329,745 estimate, according to Harrier.

– Commercial Record

Read the full article from the Commercial Record:

Oval Beach Article

 