Glenhill Drive Paving Operations

Welcome to the City of Northville 2019 Local Roads Program project portal! Here you can find information about the project and provide input.  Construction began September 9, 2019 and is expected to run through October.  Work is currently not scheduled for Sundays or holidays. Read the full Road Construction Notice.

PAVING UPDATES!

Paving is currently scheduled for the following days:

  • Morgan Court / Circle – Monday
  • Lexington Boulevard South – Monday
  • Baseline Road – Milling of existing pavement scheduled for November 5, 2019 with paving to follow shortly thereafter

As an overall update on Cady Street, the work had been delayed due to an unknown Great Lakes Water Authority (GLWA) power feed that was located within the influence of construction and discovered during excavation.  City staff, Fleis & VandenBrink, Nagle Paving, GLWA and GLWA’s contractor developed a solution to this issue and the new conduit has been installed and road construction is back on track.  Once the concrete has cured to an acceptable strength (either after Monday or Thursday, depending on the test results), Nagle Paving will begin fine grading and paving operations.  This work is tentatively scheduled for the end of the week of October 28.

Construction Update

Activities planned for the week of October 28, 2019 include:

Taft Road

  • Pavement markings installed

Cady Street

  • Fine grading
  • Final paving

Morgan Circle / Court

  • Final paving operations

Lexington Boulevard South

  • Final paving operations

Work Accomplished So Far

Activities accomplished through October 18, 2019 include:

Morgan Boulevard / Morgan Circle / Morgan Court

  • Full depth patching along Morgan Circle and Morgan Court
  • Curb replacement along Morgan Circle and Morgan Court
  • Full paving of Morgan Boulevard
  • ADA ramps poured
  • Structure adjustments and repairs as needed
  • Restoration work along roadway
  • Some detail 7 joint repairs
  • Milling of Morgan Circle and Morgan Court
  • Some paving


Cady Street

  • Milled and removed pavement and curb & gutter
  • Installed underdrain
  • Installed new conduit for GLWA power feed

Lexington Boulevard South

  • Full depth patching
  • Curb replacement
  • Structure adjustments and repairs as needed
  • Restoration work along roadway
  • Milling
  • Some detail 7 joint repairs

Glenhill Drive

  • Full depth patching
  • Curb replacement
  • ADA ramps poured
  • Structure adjustments and repairs as needed
  • Restoration work along roadway
  • Milling
  • Detail 7 joint repairs
  • Paving

MacDonald Drive

  • Full depth patching
  • Curb replacement
  • ADA ramps poured
  • Structure adjustments and repairs as needed
  • Milling
  • Detail 7 joint repairs
  • Paving

Baseline Road

  • Curb replacement
  • Structure adjustments and repairs as needed
  • Restoration work along roadway

If you have any questions or require any special accommodations, please contact the City’s engineering consultants, Fleis & VandenBrink’s onsite representative at 586.899.7015, or their office at 248.536.1997.

The 2019 City of Northville Local Roads Program includes the following projects:

  • Morgan Boulevard – Reconstruction of the south half
  • Cady Street – Reconstruction of 250′ of road and addition of eight parking spaces for the library
  • Lexington Court and Glenhill Drive – 1.5 inch mill and fill with necessary base and curb repairs
  • South half of Morgan Circle, Morgan Court, MacDonald Drive, Taft Road, and Baseline Road – 2 inch mill and fill with necessary base and curb repairs

Project Feedback

Do you have feedback regarding the proposed project? Please provide your comments, questions, or concerns below along with your contact information.