Construction Schedule Update

The following provides an update of April-May engineering activities for the SIP program:

  • Hallack Contracting has completed the following work:
    • Wythe St. – Sanitary Sewer Main from Sixth St. to Forth St, and Storm Sewer from Fifth St. to Fourth St.
    • Fifth St. – Sanitary Sewer Main from Wythe St. to Rutledge St, and Storm Sewer from Wythe St. to the creek.
    • Restored survey monuments on the 2017 project.
  • Progress Meeting #2 was held on Wednesday, April 18, 2018 with the contractor and Pentwater Wire Works (PWW). We are coordinating construction efforts to allow continued truck access to PWW.
  • Progress Meeting #3 was held on Wednesday, May 2, 2018 with the contractor and Pentwater Wire Works (PWW).
  • A meeting was held on Wednesday, May 2, 2018 with the Service Committee to give an update on the project.
  • An update notice of construction work has been sent to residences affected by the project. Also, the F&V portal link on the Village’s website will be updated with construction notices.

Anticipated work for rest of May will include the following:

  • Hallack Contracting will continue construction on the following work:
    • Wythe St. – Storm Sewer from Fourth St. to Third St and water main from Sixth St. to Third St.
    • Fifth Street – Road building from Wythe St. to Rush St.
    • Fourth St. – Sanitary Sewer Main from Sixth St. to Fifth St.
  • We will continue to update our project portal with construction activities as new or changing information becomes available.
  • Review remaining construction/punch list items from the 2017 project.