Welcome to the Village of Pentwater Street Improvement Plan Project page! Here you can find information about your project and provide input.

APRIL UPDATE

 The following provides an update of March-April engineering activities for the SIP program:

  • Hallack Contracting started work on March 19th with tree removals
  • Contractor started work on water main, sanitary, and storm drain along Fifth St. from the creek west to Carrol St
  • A Public Information Meeting was held March 22nd to review 2018 construction, approximately 25 residents were in attendance
  • Progress Meeting #1 is scheduled for Wednesday, April 3, 2018 with the contractor and utilities
  • Resident notices of construction work were placed in individual resident doors prior to the start of construction

Anticipated work for rest of April will include the following:

  • Contractor will continue work on water main, sanitary, and storm drain along Wythe St. from 6th St. to Fourth St
  • We will continue to update our project portal with construction activities as new or changing information becomes available
  • Review remaining construction/punch list items from 2017 project
  • Work Zone I – Spring, Early Summer 2018

  • Work Zone II – Early Summer, Mid-Summer 2018

  • Work Zone III – Late Summer, Fall 2018

NOTICE OF CONSTRUCTION

This notice is to inform you that starting March 19th, 2018 construction will begin on the 2018 Pentwater Street & Utility Project. This project will include the following:

  • Removal of the existing pavement and repaving of the streets indicated on the map below.
  • Various water main, sanitary, and storm drain improvements on the indicated streets.
  • Miscellaneous construction items include drainage improvements, surface restoration and pavement markings.

IMMEDIATE CONSTRUCTION SCHEDULE:
March 19th – March 30th, 2018

  • Clearing along Morris St., Fifth St. and Wythe St.

March 26th – April 30th, 2018

  • Pavement removal along Fifth St. from the creek west to Carrol St.
  • Pavement removal along Wythe St. from 6th St. to Fourth St.
  • Water main, sanitary, and storm drain along Fifth St. from the creek west to Carrol St.
  • Water main, sanitary, and storm drain along Wythe St. from 6th St. to Fourth St.
  • Place pavement on Fifth St. from the creek west to Carrol St. and on Wythe St. from 6th St. to Fourth St.

The affected streets will be closed to through traffic for the duration of the construction schedules. Access to businesses and residences will be maintained throughout the project. The contractor for the project is Hallack Contracting, Inc. from Hart MI. If you have any questions about the work, please contact the onsite Resident Project Representative. We thank you for your cooperation and patience during the construction.

For questions, please contact the following:
Gerry Klock, Resident Project Representative (231) 642-1467