City of Northville 2020 Road and Utility Construction Updates

Stanstead Road

 

Welcome to the City of Northville 2020 Road and Utility Construction Updates project portal! Here you can find information about the project and provide input. Construction began May 11, 2020 and is expected to run through November.  Work is currently not scheduled for Sundays or holidays.

 

Construction Update

Activities planned for the week of September 21, 2020 include:

 

Allen Dr

  • Restoration.
  • Top course asphalt paving.

 

Grace Street (North of 8 Mile)

  • Removals.
  • Exploratory investigation for utility work.
  • Installation of new water main.

 

Grace Street (South of 8 Mile)

  • Restoration.
  • Top course asphalt paving.

 

Grace Court

  • Prep driveways.
  • Pouring driveways.
  • Backfill and restoration.

 

If you have any questions or require any special accommodations, please contact the City’s engineering consultants, Fleis & VandenBrink’s onsite representative at 586.899.7015, or their office at 248.536.1997.

Planned Projects

The 2020 City of Northville Local Roads Program includes the following projects:

  • Base Line Road (Center to Novi Street) – 1.5 inch mill and fill – COMPLETE
  • Stanstead Road (entire length) – Full reconstruction – COMPLETE
  • Summerside Lane (entire length) – 3 inch asphalt capping with some base repairs – COMPLETE
  • Coldspring Drive (entire length) – 1.5 inch mill and fill with necessary base and curb repairs – COMPLETE
  • Sherrie Lane (entire length) – 1.5 inch mill and fill with necessary base and curb repairs – COMPLETE
  • Ford Field parking lot – Full reconstruction – COMPLETE
  • Art House parking lot – Full reconstruction – COMPLETE
  • W Cady Street (Rogers to new pavement west of Wing) – Full reconstruction and water main replacement – COMPLETE
  • Larry Drive (entire length) – Full reconstruction – COMPLETE
  • Potomac Street (entire length) – Some mill and fill and some full reconstruction – COMPLETE
  • N Rogers Street (Potomac to Main) – Full reconstruction and water main replacement  COMPLETE
  • Grace Court (entire length) – Full reconstruction and water main replacement
  • Grace Street (Baseline to Maplewood) – Full reconstruction with some water main and sanitary sewer replacement
  • Allen Drive (Novi Street to Novi Road) – Full reconstruction

Planned Projects for 2020