Project Update: Surveying, Bishop International Airport

- Project Updates

After a summer-long construction layout project at Bishop International Airport, F&V has successfully completed the project. Our survey staff provided layout for the general contractor, electrical contractor, paving contractor, and stripping contractor, along with reporting to Bishop airport engineers. Work included locating the existing airport ground control and establishing control for the construction of the new taxiway ‘R’ and the rehabilitation of taxiway ‘C’, staking the barrier locations, pavement removals, pavement milling, storm sewer, signs and lighting staking, airport pavement markings, as-built cross-sections at each lift, daily reporting and data file submission to airport engineers, and final as-built records after construction.