2021 Northville Local Streets, Water Main, and Parking Lot Improvements

Welcome to the City of Northville 2021 Local Streets, Water Main, and Parking Lot Improvements Construction Updates project portal! Here you can find information about the project and provide input. Construction is tentatively scheduled May 5, 2021 and is expected to run through September.  Work is currently not scheduled for Sundays or holidays.

Construction Update

Activities planned for the week of June 14, 2021, weather depending, include:

 

High Street

  • Utility and structure work
  • Curb installation

 

Maplewood Street

  • Curb installation

 

Fairbrook Street

  • Water main pipe bursting
  • Connecting water services to new pipe
  • Connecting new water main to existing system


Fairbrook Court

  • Water main installation


If you have any questions or require any special accommodations, please contact the City’s engineering consultants, Fleis & VandenBrink’s onsite representative at 586.899.7015, or their office at 248.536.1997.

 

Planned Projects

The 2021 City of Northville Local Streets, Water Main, and Parking Lot Improvements Program includes the following projects:

  • Northville Square Parking Lot – 1.5 inch mill and fill – COMPLETE
  • Tipping Pointe Parking Lot – Full reconstruction – COMPLETE
  • Jeffrey Drive (entire length) – 1.5 inch mill and fill with necessary base and curb repairs – COMPLETE
  • Carrington Drive (entire length) – 1.5 inch mill and fill with necessary base and curb repairs – COMPLETE
  • Maplewood Street (entire length) – Pavement removal and replacement with necessary base and curb repairs and water main replacement
  • High Street (W Dunlap to Randolph) – Full reconstruction and water main replacement
  • Wing Court (entire length) – Full reconstruction and water main replacement
  • Fairbrook Street (First to Wing) – Pavement removal and replacement with necessary base and curb repairs and water main replacement
  • Fairbrook Court (entire length) – Pavement removal and replacement with necessary base and curb repairs and water main replacement10